MAIN ACHIEVEMENTS
Customer AGIP REFINING - continuing over time
Generic and specific maintenance interventions on the systems of the Marghera Port Refinery including the general and biannual Refinery stops.
Customer EDISON TERMOELETTRICA - Year 1995
Assembly of the pump room for cooling water circulation, fire extinguishing water and closed circuit lines to the new cooling tower system. Tot. weight 120 t.
Customer FRIULANA GAS - Year 1995
Supply and assembly of process pipes and fire extinguishing water for expansion and adaptation to the new legislation of the Campoformido warehouse. Tot. weight 70 t.
Customer FISIA c/o ENEL - Years 1996-1997-1998
Supply, construction and assembly of carbon steel, stainless steel and HDPE pipes, with relative stages, assembly of the equipment and machinery of the Sewage Treatment section of the Desulphurisation system at the ENEL thermoelectric plant in Fusina (VE). Tot. weight 200 t.
Customer FISIA c/o ENEL - Years 1996-1997-1998
Supply, construction and assembly of carbon steel and stainless steel pipes, with related stages, supply, construction and assembly of monorail beams, assembly of various types of equipment of the absorption sections of the Desulphurisation system at the ENEL thermoelectric plant in Fusina (VE). Tot. weight 100 t.
Customer TECHINT c/o AGIP - Year 1996
Construction and assembly of pipes, assembly of machinery and equipment for revamping of the RZ2 system at the Marghera Port Refinery. Tot. weight 50 t.
Customer AGIP PETROLI - Year 1996
Supply, construction and assembly of metal carpentry structures for revamping of the HF1 and HF2 systems at the Porto Marghera refinery.
Tot. weight 70 t.
Customer EDISON TERMOELETTRICA - Year 1996
Supply, construction and assembly of vertical tanks for fire extinguishing water and DEMI water at the gas turbine plant in Contarina (RO). Tot. weight 100 t.
Customer EDISON TERMOELETTRICA - Years 1995-96
Construction and assembly of the supply and drain lines (including special parts) of the turbine condenser at the gas turbine plant in Contarina (RO). Tot. weight 50 t.
Customer EDISON TERMOELETTRICA - Year 1996
Upgrading of the turbogas recovery boiler of the Marghera - Azotati plant, by building and inserting no. 2 new heat exchange benches in stainless steel finned piping. Weight of benches 20 t.
Customer AGIP PETROLI - Years 1997-1998
Construction and assembly of pipes, assembly of equipment and machinery for the restructuring and upgrading of the LPG storage and loading system at the Marghera Port Refinery. Tot. weight 50 t.
Customer EDISON TERMOELETTRICA - Year 1997
Surveys, execution of the stress-analysis, verification and maintenance of the elastic suspensions of the main steam - hot superheated steam - cold superheated steam lines of thermal group no. 1 of the Marghera Levante power plant.
Customer EDISON TERMOELETTRICA - Year 1997
Construction and assembly, after removing the existing bundle, of the U-shaped piping bundle of the feed water heating exchanger of thermal group no. 1 of the Marghera Levante power plant. Weight 10 t.
Customer AGIP PETROLI - Years 1998-1999
Total extraordinary maintenance of the RC3 (catalytic reforming) and HF1 (hydro finish) systems during the general shutdown of the Marghera Port Refinery.
Customer FINCANTIERI - Years 1997-1998
Constructions 5980 - 5989. Construction and assembly of chilled and hot water pipes for air conditioning systems. Detailed engineering, construction and assembly of air conditioning ducts for entertainment rooms and passenger cabins.
Customer SIRTEC NIGI c/o AGIP - Years 1998-1999
Construction and assembly of the lower lines of the HCR system at the Venice Refinery. Weight 12 t.
Customer FINCANTIERI Years 1998-1999
Assembly of the auxiliary pipes of machines on construction 6035 zones E - F.
Customer FINCANTIERI Year 1999
Interventions of adaptation, variations and/or modifications on the service fluid lines (steam, cooling water, recovery water, air, condensate, oil, diesel, etc.) of construction 5990.
Customer FINCANTIERI Year 1999
Design, construction and assembly of 4 aluminium and glass structures for pool and bar cover of construction 6044.
Customer IROP - Year 1999-2000
Supply, construction and assembly of process lines and fire extinguishing water for expansion and adaptation to the new legislation of the Arquà Polesine warehouse. Tot. weight 100 t.
Customer T&T Years 1998 -1999
Supply, construction and assembly of mechanical theatrical devices for the ships Rotterdam, Veendam, Zaandam, of S.A. American Holland Constr. 5980 and 6035, 6036.
Customer FINCANTIERI Year 2000
Supply, construction and assembly of mechanical theatrical equipment for the ship Amsterdam, Constr. 6052, S.A. American Holland.
Customer FINCANTIERI Year 2000
Supply, construction and assembly of hydraulic systems for 2 gas tankers at the Ancona shipyard.
Customer EDISON TERMOELETTRICA – continuing over time
Mechanical maintenance of the recovery thermoelectric power plants of Marghera Levante at Marghera Azotati. Installed power 600 MW turbogas.
Customer EDISON TERMOELETTRICA - Year 2001
Construction and assembly of interconnection lines and modifications to existing plants for insertion of the new 240 MW gas turbine.
Customer FINCANTIERI Year 2000 - 2001
Assembly of process and service fluids piping in zones Q and P of the naval constructions 6065 and 6066 S.A. P.&O.
Customer FINCANTIERI Year 2001
Supply, construction and assembly of side hatches for construction vessels 6075 6076 - 6077 - 6078 - 6079 Total weight. 170 t for each ship
Customer FINCANTIERI – Year 2001
Supply, construction and assembly of hydraulic systems for command and control of AZIPOD propulsion systems, stabiliser fins, transverse propellers, turbine regulators for construction ships 6075/6079.
Customer NAVALIMPIANTI - Years 2001-2002
Assembly of cranes for the lowering of rescue systems and assembly of boats and life rafts of naval constructions 6075. N. 18 boats for each ship.
Customer HMS/ACR - Year 2001
Assembly of theatrical electro-mechanical equipment for naval constructions 6075/6079.
Customer EDISON TERMOELETTRICA – Years 2001-2002
Supply, construction and assembly of the pipes for the interception and treatment of waste fluids of the thermoelectric power station of Marghera Levante. Tot. weight 50 t.
Customer EDISON TERMOELETTRICA – Year 2002
Disassembly, reconstruction and assembly of the chromium molybdenum alloy steel supports of the high pressure steam lines, including the replacement of piping sections, of the thermoelectric power station of Marghera Levante. Tot. weight 20 t.
Customer MARIOFF CORPORATION OY (FINLAND) – Year 2002
Installation of the fog fire safety system (Hi-Fog System)on the naval constructions 6075 - 6079 service areas.
Customer TRIVENGAS – Years 2002–2003
Executive and detailed engineering, supply, construction and assembly of the new supply/discharge lines to/from pump-compressor room, bottling room, tanker ramps of the LPG depot in Mirano (VE) Total weight. 35 t pipes.
Customer AQUATER – Years 2003–2004
Construction and assembly of pipes, assembly of equipment and machinery for revamping of the TE system (effluents treatment) of the ENI refinery at Marghera Port (VE). Tot. weight piping 190 t.
Customer TECHINP/ W ELCO – Year 2003
Assembly of service carpentry at the D102-N reactor of the HF1 plant Eni Refinery in Venice. Tot. weight 35 t.
Customer BRENTA GAS – Years 2003-2004
Executive and detailed engineering, supply, construction and assembly of the new supply/discharge lines to/from pump-compressor room, bottling room, tanker ramps of the LPG depot in Mira (VE) Total weight. 60 t pipes
Customer TECHINT – Year 2004
Assembly Carpentry, equipment and machinery, construction and assembly of the pipes of the RZ1 (sulphur recovery) system ravamping of the ENI Refinery at Marghera Port (VE) Total weight. 70 t pipes
Customer E.n.i. Refinery of Venice - Year 2005
RZ1 system putting on line and start-up. General maintenance of RC3 system with replacement of the Packinox reactor/regenerator weight 70 t. laying surface 5 ml reactor height 23 ml.
Customer Edison Termoelettrica – Years 2005-2006
Disassembly of the appliances, pipes and accessories of the steam generator group no. 1 and their reassembly in another area of the Marghera Levante plant.
Customer FINCANTIERI – Years 2005-2006 - Naval Construction 6129
Assembly of dividing doors, side doors and splash doors, connected hydraulic systems, hydraulic systems to control and adjust the ship's trim, emergency hydraulic systems, oxygen/acetylene distribution system, carpentry and electromechanical works for the on-board theatre, carpentry and electromechanical works for aft pool cover.
Customer FINCANTIERI – Years 2006-2007 - Naval Construction 6127
Assembly of side doors, connected plumbing systems, plumbing systems for ship trim control and adjustment, emergency plumbing systems, oxygen/acetylene distribution system, carpentry and electromechanical works for the on-board theatre.
Customer FINCANTIERI – Years 2007-2008 - Naval Construction 6149
Hydraulic systems for ship trim control and adjustment, emergency hydraulic systems, carpentry and electromechanical works for the on-board theatre.
Customer Edison Thermoelectric - Year 2008
System flexibilisation - Construction and assembly of the steam piping system (High Pressure Steam, Medium Pressure Steam, High Pressure Condensate pipes) at the Marghera Levante power plant.
Customer E.n.i. Refinery of Venice - Year 2008
General maintenance of PV1 system; general maintenance of the RZ1 system; general maintenance of HF2 system; general maintenance of RC3 system.
Customer FINCANTIERI – Years 2008-2009 – Naval constructions 6155-6164
Hydraulic systems for ship trim control and adjustment, emergency hydraulic systems, carpentry and electromechanical works for the on-board theatre.
Customer E.n.i. Refinery of Venice - Year 2009
Replacement of monitoring towers at the S. Leonardo Port.
Customer FINCANTIERI – Year 2009 – Naval construction 6187
Hydraulic systems for ship trim control and adjustment and emergency hydraulic systems.
Customer FINCANTIERI – Years 2009-2010 - Naval construction 6181
Hydraulic systems for ship trim control and adjustment, emergency hydraulic systems, carpentry and electromechanical works for the on-board theatre.
Customer FINCANTIERI – Years 2010-2011 - Naval construction 6188
Hydraulic systems for ship trim control and adjustment and emergency hydraulic systems. Installation of thrusters flow deflectors.
Customer FINCANTIERI – Years 2010-2011 - Naval construction 6189
Hydraulic systems for ship trim control and adjustment and emergency hydraulic systems. Local Engine Equipment Systems - Flushing with oil and water and chemical treatment of pipe pickling. Installation of thrusters flow deflectors.
Customer FINCANTIERI – Year 2011 – Naval construction 6201
Local Engine Equipment Systems – Flushing with high temperature cooling system water (pump with a flow rate of 1,300 m3 used).
Customer E.n.i. Refinery of Venice - Year 2011
General maintenance of PV1 system; general maintenance of the RZ1 system; general maintenance of RC3 system.
Customer Saipem – Year 2011
A.P.I. steam recovery system at the E.n.i. Refinery of Marghera Port - Venice.
Customer FINCANTIERI – Years 2011-2012 – Naval construction 6223 and 6224
Hydraulic systems for ship trim control and adjustment and emergency hydraulic systems. Installation of watertight and splash compartment doors. Installation of fire extinguishing system with atomisation in laundry rooms.
Customer E.n.i. Refinery of Venice - Year 2012
Boiler B1 - Welding operations inside the cylindrical bodies
Customer FINCANTIERI – Years 2012-2013 - Naval construction 6203
Hydraulic systems for ship trim control and adjustment and emergency hydraulic systems. Grease treatment system installation. Mechanical assembly of thruster engines. Installation of machines and theatrical carpentry.
Customer E.n.i. Refinery of Venice – Year 2013-2014 – Green Refinery Step 1 Project
Maintenance systems HCR-Amine-SPL/GPL-SW 3-SW 2-PV1-VB-IB-RC3.
Customer E.n.i. Refinery of Venice – Year 2014 – Green Refinery Step 1 Project
Revamping for systems conversion HCR-Amine-SPL/GPL-SW 3-SW 2-PV1-VB-IB-RC3.
Customer FINCANTIERI – Year 2014 – Naval construction 6231
Hydraulic systems for ship trim control and adjustment and emergency hydraulic systems. Installation of watertight and splash compartment doors.
Customer FINCANTIERI – Year 2014 – Naval construction 6236
Hydraulic systems for ship trim control and adjustment and emergency hydraulic systems. Installation of watertight and splash compartment doors. Grease treatment system installation. Diesel generators mechanical assembly.
Customer FINCANTIERI – Year 2014 – Naval construction 6237
Hydraulic systems for ship trim control and adjustment and emergency hydraulic systems. Installation of watertight and splash compartment doors. Diesel generators mechanical assembly.
Customer FINCANTIERI – Year 2014 – Naval construction 6241
Hydraulic systems for ship trim control and adjustment and emergency hydraulic systems. Installation of watertight and splash compartment doors. Grease treatment system installation. Diesel generators mechanical assembly.
Customer FINCANTIERI – Year 2015 – Naval construction 6232
Hydraulic systems for ship trim control and adjustment and emergency hydraulic systems. Installation of watertight and splash compartment doors.
Customer FINCANTIERI – Year 2015 – Naval construction 6245
Hydraulic systems for ship trim control and adjustment and emergency hydraulic systems. Installation of watertight and splash compartment doors.
Customer FINCANTIERI – Year 2015 – Naval construction 6250
Hydraulic systems for ship trim control and adjustment and emergency hydraulic systems. Installation of watertight and splash compartment doors.
Customer FINCANTIERI – Year 2015 – Naval construction 6251
Hydraulic systems for ship trim control and adjustment and emergency hydraulic systems. Installation of watertight and splash compartment doors.
Customer FINCANTIERI – Year 2015 – Naval construction 6256
Hydraulic systems for ship trim control and adjustment and emergency hydraulic systems. Installation of watertight and splash compartment doors.
Customer FINCANTIERI – Year 2016 – Naval construction 6226
Hydraulic systems for ship trim control and adjustment and emergency hydraulic systems. Installation of watertight and splash compartment doors.
Customer FINCANTIERI – Year 2016 – Naval construction 6243
Hydraulic systems for ship trim control and adjustment and emergency hydraulic systems. Installation of watertight and splash compartment doors. Grease treatment system installation. Diesel generators mechanical assembly.
Customer FINCANTIERI – Year 2016 – Naval construction 6246
Hydraulic systems for ship trim control and adjustment and emergency hydraulic systems. Installation of watertight and splash compartment doors.
Customer FINCANTIERI – Year 2016 – Naval construction 6257
Hydraulic systems for ship trim control and adjustment and emergency hydraulic systems. Installation of watertight and splash compartment doors.
Customer FINCANTIERI – Year 2017 – Naval construction 6244
Hydraulic systems for ship trim control and adjustment and emergency hydraulic systems. Installation of watertight and splash compartment doors. Grease treatment system installation. Diesel generators mechanical assembly.
Customer FINCANTIERI – Year 2017 – Naval construction 6253
Hydraulic systems for ship trim control and adjustment and emergency hydraulic systems. Installation of watertight and splash compartment doors.
Customer FINCANTIERI – Year 2017 – Naval construction 6258
Hydraulic systems for ship trim control and adjustment and emergency hydraulic systems. Installation of watertight and splash compartment doors.
Customer FINCANTIERI – Year 2017 – Naval construction 6268
Hydraulic systems for ship trim control and adjustment and emergency hydraulic systems. Installation of watertight and splash compartment doors.
Customer FINCANTIERI – Year 2018 – Naval construction 6254
Hydraulic systems for ship trim control and adjustment and emergency hydraulic systems. Installation of watertight and splash compartment doors.
Customer FINCANTIERI – Year 2018 – Naval construction 6271
Hydraulic systems for ship trim control and adjustment and emergency hydraulic systems. Installation of watertight and splash compartment doors.
Customer FINCANTIERI – Year 2018 – Naval construction 6272
Hydraulic systems for ship trim control and adjustment and emergency hydraulic systems. Installation of watertight and splash compartment doors. Grease treatment system installation. Diesel generators mechanical assembly.
Customer FINCANTIERI – Year 2018 – Naval construction 6287
Hydraulic systems for ship trim control and adjustment and emergency hydraulic systems. Installation of watertight and splash compartment doors.
Customer FINCANTIERI – Year 2019 – Naval construction 6273
Hydraulic systems for ship trim control and adjustment and emergency hydraulic systems. Installation of watertight and splash compartment doors. Grease treatment system installation. Diesel generators mechanical assembly.
Customer FINCANTIERI – Year 2019 – Naval construction 6275
Hydraulic systems for ship trim control and adjustment and emergency hydraulic systems. Installation of watertight and splash compartment doors.
Customer FINCANTIERI – Year 2019 – Naval construction 6278
Hydraulic systems for ship trim control and adjustment and emergency hydraulic systems. Installation of watertight and splash compartment doors. Grease treatment system installation. Diesel generators mechanical assembly.
Customer FINCANTIERI – Year 2019 – Naval construction 6279
Hydraulic systems for ship trim control and adjustment and emergency hydraulic systems. Installation of watertight and splash compartment doors.
Customer FINCANTIERI – Year 2019 – Naval construction 6281
Hydraulic systems for ship trim control and adjustment and emergency hydraulic systems. Installation of watertight and splash compartment doors.
Customer FINCANTIERI – Year 2019 – Naval construction 6283
Hydraulic systems for ship trim control and adjustment and emergency hydraulic systems. Installation of watertight and splash compartment doors.
Customer FINCANTIERI – Year 2019 – Naval construction 6288
Hydraulic systems for ship trim control and adjustment and emergency hydraulic systems. Installation of watertight and splash compartment doors.
Customer FINCANTIERI – Year 2019 – Naval construction 6306
Hydraulic systems for ship trim control and adjustment and emergency hydraulic systems. Installation of watertight and splash compartment doors.
Customer E.n.i. Refinery of Venice – Years from 2015 to 2020 (still in progress)
Generic maintenance and assembly contract. Green Refinery project phase 2 interconnecting acid gas treatment